Category | Assignment | Subject | Management |
---|---|---|---|
University | Singapore University of Social Science | Module Title | BUS353 Project Management |
Answer all questions in this section.
The Objective of this ECA
To provide an opportunity for students to apply the knowledge learnt in the course and to develop/sharpen the necessary technical skills and knowledge in project management.
Please note that:
You are required to compose a report for Section A.
PROJECT: Implementing An Air Taxi System
Background
Singapore is a small country. There is limited land that can be catered to road usage. However, many economic activities need to be carried out by transportation. Hence, alternative modes of transportation have to be explored.
Air Taxi System (ATS) can be used to transport passengers for short to medium distances by applying Advanced Air Mobility (AAM) technologies, which include vertical takeoffs, autonomous capabilities and fully electric systems. The vehicle is quiet, environmentally friendly, can take off in small areas and is driverless by remotely controlled from a centre. It has the potential to offer alternatives to land transportation, particularly in congested cities or hard-to-reach rural regions. Currently, there are pilot air taxi services in several parts of the world. However, there is no unified ATS standard yet.
Cross Country Transport (CCT) is a transportation company that provides bus, taxi, and train services. CCT’s senior management is interested to pilot an air taxi service between Sentosa Cove and Marina Bay. However, as a transportation company, CCT does not have the knowledge and resources to develop the system.
Air Bot Creator (ABC) is a technology company which designs and manufactures drones for surveillance and logistic industries. ABC intends to extend its capabilities to develop an ATS.
Question 1a
Through an economic platform provided by the government to match Business to Business (B2B) partners, CCT came into contact with ABC. After intensive discussions, CCT decided to outsource the development of its pilot air taxi service to ABC. Both parties call it the Air Taxi System (ATS) Project.
Relate four (4) approaches of Principled Negotiation, each to a situation that CCT can adopt when negotiating with ABC on an item or issue about the ATS Project.
You must present your answer in the following format:
CCT shall apply the approach: ___________ (name the approach) in negotiating ___________ (identify an item or issue) with ABC. Details: ___________ (describe the situation, how CCT can apply the approach and the reason of doing so).
You should limit your essay for Question 1(a) to a maximum of 450 words and indicate the word count at the end of your answer.
Question 1b
ABC’s CEO, Mr James Tan, gathered the following staff to form the ATS Project team:
Before the project starts, James briefed you on the management’s expectations:
Based on the CEO’s directions, you are required to appraise the priorities of the project and construct a project priority matrix.
Note: Each criterion can be assigned to only one unique priority.
Do You Need BUS353 Assignment of This Question
Order Non Plagiarized AssignmentYou have conducted a pre-project discussion and worked out the project activities, as shown in Table 1.
Activity No. | Task Name | Duration (days) | Predecessors | Resource Names |
---|---|---|---|---|
1 | Air Taxi System (ATS) Project | |||
2 | Study CCT requirements | 5 | PM (See *Note below), Ravi, Hannah | |
3 | Set up Control Centre | 10 | 2 | Ravi |
4 | Developed taxi application software | 18 | 2 | Hannah |
5 | Develop control centre software | 15 | 2 | Hannah |
6 | Design vehicle chassis | 18 | 2 | Ravi, Chassis[1] |
7 | Select vehicle engine | 15 | 6 | Ravi, Engine[1] |
8 | Assemble vehicle | 15 | 7 | Ravi, Production[1] |
9 | Install control centre computer | 10 | 3,5 | Hannah, Computer[1] |
10 | Construct taxi landing stations | 12 | 6 | PM, Construction[1] |
11 | Test application software | 15 | 4,8 | Hannah |
12 | Test control centre software | 7 | 9,11 | Hannah |
13 | Test overall system | 12 | 10,11,12 | Ravi, Hannah |
14 | Certified by CAAS | 10 | 13 | PM |
15 | Train CCT Staff | 5 | 14 | Ravi, Hannah |
16 | Hand over ATS | 1 | 14,15 | PM |
Table 1: Activity List for Air Taxi System (ATS) Project
*Note: You must use your surname instead of “PM” in the MS Project Resource Sheet and Column.
To prepare an initial costing for budget approval, you gather the following unit costings:
Resource Name | Type | Max | Standard Rate |
---|---|---|---|
PM (See *Note above) | Work | 100% | $140/hr |
Hannah | Work | 100% | $130/hr |
Ravi | Work | 100% | $120/hr |
Table 2: Standard Rates for Work Type Resources
Resource Name | Type | Standard Rate |
---|---|---|
Chassis | Material | $60,000 |
Engine | Material | $40,000 |
Computer | Material | $10,000 |
Production | Material | $90,000 |
Construction | Material | $80,000 |
Table 3: Standard Rates for Material Type Resources
Notes on the costs:
Notes on using MS Project for Q2 & Q3:
2. The Public Holidays that may fall within the project period are:
If a Public Holiday falls on a Sunday, the following Monday will be a Public Holiday in lieu. If that Monday is another Public Holiday, Tuesday will be the Public Holiday in lieu. There will be no holiday-in-lieu for a Public Holiday that falls on a Saturday.
To mark in MS Project all Public Holidays and Holiday-in-lieu as NonWorking:
Click Project-> Change Working Time. Enter the name of the holiday and the date. Then click Details ->click Nonworking.
Buy Custom Answer of This BUS353 Assessment & Raise Your Grades
3. To enter the name, resource type and cost of each resource item in Tables 2 & 3 into the Resource Sheet: Click View->Gantt Chart (Leftmost icon)->More View->Resource Sheet Enter the name of the resources, standard rates, but leave the cost per use as $0. Choose Accrue as Prorated.
4. If only one member needs to work on a Saturday or Sunday for a particular activity, you must change his/her calendar so as not to affect parallel activities done by other members.Click View -> Resource Sheet. Right-click on the resource to change. Click Information -> Click “Change Working Time”. Enter a description in Name, the chosen date, then click Detail-> Working-> Set the working time (or choose default time). You are advised to do one day per row and check your data before applying it.
5. Click View->Gantt Chart, then View->Table->Entry to enter the Task Name, Duration, and Predecessors into the respective columns.Do not change the order of activities, durations, predecessor relationships, or the resources assignments until needed. You are not required to rearrange the list into a Work Breakdown Structure. Use the dropdown list in the Resource Names’ cells to assign the resources.
6. Set Activity 1 as the higher-level activity by highlighting all activities below and right indent them to second level.Then click Project -> Project Information -> Set Start Date as dictated by the CEO. Right click on Activity 1 to access its Information; Under Advanced Tab, set Deadline as dictated by the CEO.
7. To view critical tasks, click Gnatt Chart Format -> click Critical Tasks.
8. To see all resource conflicts, select all tasks, right click to choose Auto Schedule, then Resource Tab ->Clear Leveling. Observe any resource conflicts.
9. Diagrams, charts, tables, graphs, and relevant project outputs may be shown as images. These must be appropriately formatted and presented so that they can be viewed comfortably.
Question 2a
Construct a Gantt Chart (after Clear Leveling) with Information (i), Task Mode, Task Name, Duration, Start Date, Finish Date, Predecessors, and Resource Names columns shown in a single diagram. Hence, state the project completion date and explain any resource conflicts.
Question 2b
You need to solve the conflicts within the project deadline. Due to the specialised skills of the team members in this intensive project, resource conflicts cannot be resolved by splitting the task, member multitasking, transferring the task to other members, or adding more people. The members will not be working beyond eight (8) hours per day. At this moment, they do not want to work on weekends. Hence, you should try to resolve the conflicts within the available slacks. Set up the approach below:
Right-click on the task with the conflict that has the smallest Task (i.e., Activity) ID. Select “Reschedule to Available Date”.
Proceed to the next task below with conflict. Repeat the above operations one at a time until all tasks with conflicts that could be resolved are completed. There is no need to use any additional methods now to resolve the conflicts.
You must explain the outcome of your action in each of the steps above and state the eventual project completion date if it changes.
Note: There is no need to show diagrams for Question 2(b).
Question 2c
You try to push the finish date further to resolve all the resource conflicts without adding demands on the resources. Do the following:
First, select all tasks, right-click to choose Auto Schedule, then Resource Tab -> Clear Levelling. Choose Entire Project.
Then do Auto leveling by clicking Resource-> Leveling Option -> Tick the buttons “Automatic” and “Level Entire Project”. Uncheck all the boxes below. Then click Level All.
Assess the changes due to this resource leveling operation. Identify the finish date and comment on the impact.
Note: There is no need to show diagrams for Question 2(c).
Question 2d
You are aware of the need to hand over the system by the deadline. You need to solve the problem by exercising your Project Manager authority.
First, do Clear Levelling. Then select the items you want to change, followed by Level All.
Explain the changes you make in MS Project so that the deadline can be met.
Note: You should show the settings in MS Project for Question 2(d).
The CEO approves the changes made in Question 2. Set the Status Date (Project -> Status Date) as 5 Feb 2025. Save this as a Baseline Plan (Project -> Set Baseline -> check Entire project), which will be used to evaluate the project performance at a later stage.
As the project progressed, the following incidents occurred:
Note: This special allowance of delaying the deadline does not apply to the situations in Question 2.
Update all relevant activities and costs in the MS Project File to incorporate the changes due to incidents (i) and (ii).
The project went on till completion. Set Status Date to the working day after the last activity, then update the MS Project file. (Project->Update Project, Click Entire Project).
Question 3a
Set up in a single diagram the Tracking Gantt Chart view of MS Project with Information (i), Task Mode, Task Name, Duration, Start Date, Finish Date, and Predecessor columns shown. State the project completion date.
Question 3b
Present a MS Project Cost Report or Table with the Cost Performance Index (CPI). State the values for Budgeted Cost At Completion (BAC) and Estimated Cost At Completion (EAC). Formulate the Cost Performance Index (CPI) and compute the final CPI manually.
Question 3c
Discuss two (2) actions that could have been taken to prevent the two incidents during the project implementation period from happening or to reduce their impacts.
Note: Discuss one action for each incident.
Are You Looking for an Answer of This BUS353 Assignment
Answer all questions in this section.
The ABC’s CEO has scheduled a meeting one week after the project completion for you, the Project Manager for the Air Taxi System (ATS) Project, to illustrate to the Senior Management the following items:
Prepare a video recording of your presentation of at least 3 minutes but not exceeding 6 minutes. Refer to Canvas T/RESIT course site > Assignments > ECA_VIDEO for the step-by-step guide on how to submit the video.
Answer all questions in this section.
Prepare a set of PowerPoint presentation slides upon which the video presentation is based. Please note that the PowerPoint file must be converted to a PDF file before submission to Canvas.
If you are having trouble with your assignment for BUS353 Project Management, then you have reached the right place. Our expert team provides management assignment help specially designed for students. We are here for you, providing free assignment examples written by our expert PhD writers. We cover all the important areas of Intercultural Business Practice. If you need the best assignment writing services, then we are here to provide the best services.
If you want to see the related solution of this brief, then click here: Project Management
Let's Book Your Work with Our Expert and Get High-Quality Content