This assignment is designed to be completed by a group of 5 students (in the case when the student number is not a multiple of 5, 4 or 6 students may be permitted for 1-2 groups). Students may choose to have fewer members in one group, but need to note that groups with fewer students are expected to complete all the tasks, and will be subject to the same marking standard. This document sets out what is required to be done by each group.
Working for a construction planning company, your group needs to develop a tender program, a basis of schedule document and associated diagrams and documents for a construction contractor.
An Institutional building of three levels is to be built for a client. Attached you can find a set of drawings for your use, but the fully detailed working drawings are not available. It means you need to make assumptions about the design where required. (This is a normal occurrence for tendering)
Your task is to develop the relevant planning suite of documents as follows:
Get the Solution of this BLDG2023 Assessment. Hire Experts to solve this assignment before your Deadline
Order Non-Plagiarised AssignmentThis is a group assignment.
Your group should approach the assignment according to the following guidelines and complete all the tasks:
1. Study the plans/drawings provided. As the detailed design is not available, you will need to establish the approximate dimensions of the site and the approximate dimensions of unspecified building components, compliant with the information given in the attached drawings.
2. You can assume the building is built in any state/council area of Australia, no need to be restricted by the street names provided in the drawings.
3. Prepare a basis of schedule document including scope analysis, the site dimensions and conditions, local council requirements, local climate and weather information, construction constraints, contingencies, etc.
4. Prepare a site establishment plan that includes drawings of the site at the initial, mid and final phases of construction. You may use any drawing software of your choice. This could be a single drawing or multiple drawings in stages showing:
5. Prepare a Work Breakdown Structure. The WBS should reflect your construction strategy and should show the different stages of construction. A list of typical construction activities is given in the attached file for your reference, but you do Not have to be restricted by it.
6. Calculate activity durations using work method statements (WMS) for 20 typical activities (refer to class lectures for an example of a WMS). It is recommended that the schedule do not exceed 120 activities in total, but this depends on how detailed your schedule is.
Stuck on your BLDG2023 Construction Planning Group? Don't worry! Our Construction Management Assignment Help service is the best for you. If you need help with assignments, our expert PhD writers will provide you with original content. And yes, you will also get free assignment samples, which will give you a perfect idea of how to write a top-quality assignment. Don't worry about the deadline, as we guarantee on-time delivery. Contact us now for high-quality and plagiarism-free work and boost your grades!